Contractor delay
Contractor delay (sometimes referred to as culpable delay) is an expression commonly used to describe any delay caused by a Contractor Risk Event (an event or cause of delay or disruption which under the contract is at the risk and responsibility of the Contractor).
The Society of Construction Law Delay and Disruption Protocol distinguishes between:
- Contractor Delay to Progress, which is a delay which will merely cause delay to the Contractor’s progress without causing a contract completion date not to be met.
- Contractor Delay to Completion, which is a delay which will cause a contract completion date not to be met.
It is sometimes referred to as non-excusable delay.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.
ECA welcomes procurement reforms
Public spending must back British jobs and skills.
Campaigning for Edinburgh: the Cockburn Association 1875-2049
The role of the civic voice in protecting character. Book review.
CIOB photography competition is open for entries.
ECA Edmundson apprentice of the year award
Finalists announced.
Major new study exposes serious knowledge gaps.
Generating energy from internal light as well as sunshine.
ECA welcomes plans to strengthen subcontractor quality control.
Combining mid-career qualifications with experience broadens career opportunities.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.

















